[The renovation works of the rainwater and sewer networks in Los Dolores are progressing at a good pace (03/02/2021)

| The works consist of the installation of 381 meters of pipes that will replace the previous fiber cement pipes and have a budget of 191,241 euros that will be financed with the surplus of the water service concessionaire | The execution of the renovation works of 381 meters of the sanitation and supply networks on San Juan Bosco avenue in Los Dolores continues at a good pace.

The project, which has a budget of 191,241 euros, is financed through the surplus of the water service concessionaire. The renewal of the pipes was a very necessary infrastructure for the residents of Los Dolores since, until now, the sewerage and rainwater network was unitary, had an insufficient diameter, which caused constant obstructions and flooding both on public roads and in the houses themselves and, in addition, they were made of fiber cement. “Traffic jams in the network were a constant in the lives of the residents of Los Dolores, even outside of rainy episodes, so this is a highly demanded work.

The works are progressing at a good pace and, if everything continues as planned, this infrastructure will be completely finished by mid-April ”, explained the mayor, Ana Belén Castejón. It should be remembered that the works began on January 20 and that they have an execution period of 3 months.

In addition, on San Juan Bosco avenue, the renewal of these pipes will also affect the streets Subida al Plan, Suspiro, Montagut, Ecuador, Paraguay, Río Júcar, Río Guadiana, Marqués de Fuente Sol, Montseni, Montblanc and Castillo del Buen Amor . MORE THAN 3 MILLION EUROS TO EXECUTE 11 PROJECTS The mayor highlighted that 11 projects worth more than three million euros have already been approved and are in the bidding phase, charged to the surplus of the water service concessionaire, of which 8 have already started. These projects are being executed, in addition to Los Dolores, on Calle Mayor de Canteras; Casas del Pino, in the Plan; Paseo del Malecón, in Alums; several streets of Pozo Estrecho; as well as the hydraulic works on Saura Street; in Santa Ana (APICES) and in El Albujón. On the contrary, the renovation works of the sanitation network in Los Urrutias, Los Nietos and on Subida San Diego Street are still pending, all three of which are already in the bidding phase; The LLano del Beal and the Plaza de España collector, whose projects are being finalized.

function { ;(, , {});}

Source: Ayuntamiento de Cartagena

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información