Portal de Cartagena

www.portaldecartagena.com

Cartagena  - SpanishCartagena  - English
detail of Cartagena

 

The filling of the Via Verde del Barrio Peral be ready in late August (22/07/2010)

The works that will make the old route of the railway from Barrio Peral a cyclable Greenway, which began late last month, are on schedule, so that the work of filling with earth and brush cleaning of the entire route are scheduled to be finished in late August.

To date, 20 percent of the work is finished and is proceeding to fill the trenches and embankments of the old route up to leaving the streets, which is being used in around 50,000 cubic meters of earth.

After this performance, will begin the task of road concreting and landscaping of the environment that accompany it, with the definition of a cycleway and lighting, to meet the deadline of eight months will do that for the first quarter of 2011 we star turn on this initiative Plan E.

The budget for this project is $ 1.5 million.

Source: Ayuntamiento de Cartagena

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información